The Olympic flame arrives in Rome on Thursday because the Milan-Cortina Winter Games close to, however organisers are dashing to verify all the pieces is prepared for a sprawling occasion unfold throughout an unlimited space of northern Italy.
With simply two months till the beginning of the 2026 Winter Olympics, which run over February 6-22, issues stay over a lot of websites, most notably the Santa Giulia Arena close to Milan which is scheduled to host the ice hockey event however continues to be a constructing web site.
And whereas the flame takes a 60-day journey round Italy on its solution to Milan, the place the primary opening ceremony can be held, one other Olympic custom is being revered within the type of a late sprint to finish works at a clutch of venues.
READ ALSO: 100 days to go: Will Italy be prepared for the 2026 Winter Games?
Milan-Cortina’s organising committee declined to touch upon some alarming stories, however Christophe Dubi, the International Olympic Committee’s Executive Director of the Games, admitted  that “stress” was felt.
“You will know when you had been concerned with Paris 2024 (summer season Olympics), some issues are delivered late as a result of that is simply the character of the enterprise; essentially the most important investments are made within the last months,” Dubi mentioned on Wednesday on a go to to 2030 Winter Olympic websites in France.
As properly as Santa Giulia, the snow park in mountain city Livigno which is able to host snowboarding and freestyle snowboarding occasions can also be below scrutiny.
This week Michel Vion, the Secretary General of the International Ski Federation (FIS), expressed concern to AFP about delays to the location’s synthetic snow system, with out which the jumps and ramps wanted for the occasions can’t be constructed.
“Apparently, the hillside reservoir is accomplished however they have not obtained the permits to fill the lake but,” mentioned Vion.
“A reservoir with out water is sort of problematic. We are nonetheless a bit involved as a result of the necessity for snow is critical for these disciplines.”
Â
SiMiCo, the state-owned firm liable for delivering the Olympic venues, advised AFP that the usage of snow cannons must be attainable by the center of subsequent week.
“The low temperatures we’ve got in Livigno imply that we’re not anxious in any respect,” mentioned SiMiCo CEO Fabio Massimo Saldini.
Advertisement
But it’s Santa Giulia which continues to be the most important concern, as the sector is meant to host stars of the world’s greatest ice hockey League the NHL, who’re returning to the Games after a 12-year absence.
Luc Tardif, the pinnacle of the International Ice Hockey Federation, fumed to Radio Canada that “the services in Milan are lower than commonplace”.
But the venture’s personal developer Eventim says that the sector can be delivered in January, a month later than initially scheduled, as “580 employees on two shifts” rush to get it prepared.
Milan-Cortina organisers confirmed on Wednesday {that a} key take a look at occasion for the sector can be held on January September 11, with seven membership matches being performed on the rink over these three days.
Meanwhile at Cortina d’Ampezzo it is a cable automotive somewhat than a contest venue which is inflicting complications.
The Apollonio-Socrepes ski elevate is meant to move spectators to the ladies’s alpine snowboarding occasions and alleviate congestion within the stylish resort within the Dolomite mountains.
Advertisement
But works solely started in July on account of a mixture of authorized challenges and terrain points, which means that organisers have needed to restrict ticket gross sales for followers who need to see stars like Mikaela Shiffrin, Lindsey Vonn and native hero Sofia Goggia compete on the well-known Olimpia delle Tofane piste.
A weary sounding Saldini insisted that “the works can be accomplished in time for the Games”.
“Italy can be prepared,” he added.
“We had been additionally advised that the curling rink and bobsleigh observe would not be prepared however every time we bought it achieved.”
The bobsleigh observe at Cortina was an enormous query mark for the Games, on account of its building solely beginning in February final yr following a political firestorm attributable to organisers initially deciding to carry the sliding occasions overseas.
The International Luge Federation’s competitors director Matthias Boehmer advised AFP that there are “no negatives” in regards to the observe following the success of current take a look at occasions.
“For us, the Olympics might begin tomorrow.”